National Grid’s contractor, Posillico Environmental, is implementing the New York State Department of Environmental Conservation (NYSDEC)-approved Excavation Interim Remedial Measure (IRM). We anticipate this work to continue through the end of the year. We will be conducting community air monitoring and vibration monitoring during this project.
No remediation site activities will take place from Monday, November 27, 2017 to Wednesday, November 29, 2017. Remediation site activities are anticipated to resume Thursday, November 30, 2017.
On-going activities (beginning again 11/30/17):
- Tent structure assembly (Area 3)
- Import backfill
- Backfill of Area 1 cells
Recently completed activities:
- Excavation and backfill of areas inside tent structure (Area 1)
- Transportation and disposal of excavated material (Area 1)
- De-watering of excavations (Area 1)
Upcoming work activities:
- Tent structure air handlers (Area 3)
- Electrical wiring of air handler units
- Excavation of Area 3 cells
- Backfill of Area 3 cells
- Breakdown and removal of tent structure over Area 1
- Transportation and disposal of excavated material (Area 3)
Community Air Monitoring Plan Summary
Continuous community air monitoring is on-going.
There were no 15-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOC) and Particulate Matter (PM-10) [dust].
Contact Information
National Grid will provide updates as the work at the site proceeds. For more information, please leave a message on our hotline at (718) 982-7349 or email us at info@dangmanparkmgpsite.com
Website Update Information
National Grid will provide an activity update for neighbors of the former Dangman Park MGP site with developments related to the investigation and remediation of the Site. During the remedial construction phase, National Grid provides a weekly update on activities related to the remediation of the Site. The updates describe the work being done on and near the Site, and provide an outlook and schedule for upcoming work, including information about work that may impact normal community activities. All updates are archived under the Key Documents tab of this website.
Assembly and erecting of Tent 2 over Area 3
Assembly and erecting of Tent 2 over Area 3
View of both tent structures