Weekly Update - September 8, 2017
National Grid and its contractors are at the former Dangman Park MGP site conducting the New York State Department of Environmental Conservation (NYSDEC)-approved Excavation Interim Remedial Measure (IRM).
On-going activities:
- Mobilization of equipment and supplies
- Transport and dispose concrete, asphalt and debris
Recently completed activities
- Installation of interior fence lines
- Demolition of concrete slab and asphalt
Upcoming activities:
- Continued mobilization of equipment and supplies
- Deliveries of sheet piles
- Delivery of ABI drill rig
- Trenching along sheet pile installation locations
- Installation of sheet piles in Area 1
Community Air Monitoring Plan Summary
The Community Air Monitoring Program background (baseline) monitoring began 9/6/2017.
Contact Information
National Grid will provide updates as the work at the site proceeds. For more information, please leave a message on our hotline at (718) 982-7349 or email us at info@dangmanparkmgpsite.com
Website Update Information
National Grid will provide an activity update for neighbors of the former Dangman Park MGP site with developments related to the investigation and remediation of the Site. During the remedial construction phase, National Grid provides a weekly update on activities related to the remediation of the Site. The updates describe the work being done on and near the Site, and provide an outlook and schedule for upcoming work, including information about work that may impact normal community activities. All updates are archived under the Key Documents tab of this website.
Concrete removed from Area 1 Excavation B
Stockpile of concrete and asphalt
Asphalt removed from Area 2