Site Work - Mobilization - Week of 8/21/17
National Grid and its contractors are mobilizing to the former Dangman Park MGP site to begin the New York State Department of Environmental Conservation (NYSDEC)-approved Excavation Interim Remedial Measure (IRM).
On-going activities:
- Mobilization of equipment and supplies;
- Installation of erosion and sediment controls.
Recently completed activities:
- None.
Upcoming activities:
- Continued mobilization of equipment and supplies;
- Conduct utility survey.
Community Air Monitoring Plan Summary
The Community Air Monitoring Program will begin when ground intrusive activities begin.