Update – February 2012
No field work is scheduled to be conducted during the weeks of January 23, January 30 and February 6.
The non-aqueous phase liquid (NAPL) delineation phase of work is ongoing to determine the extent of the NAPL impacts. Activities for the weeks of February 13 and February 20, 2012 include soil boring drilling adjacent to the shopping center property and on the Trump Village property. Soil samples are being collected from the soil borings and submitted to a laboratory for chemical analyses. The soil borings are being drilled using sonic drilling techniques. In addition, permanent monitoring wells will be drilled and installed during the weeks of February 13th and 20th.