Upcoming Site Work:

In April 2024, National Grid and its contractors completed the installation of eight (8) monitoring wells on OU 1 of the former K-Dangman Park MGP Site.  The purpose of the wells is to monitor the post-remedial groundwater conditions. The work was conducted with oversight by the New York State Department of Environmental Conservation (NYSDEC) under an approved work plan.

Groundwater samples were collected in May 2024 and a groundwater report is currently being prepared for the NYSDEC.  Future groundwater sampling will be conducted on an annual basis.